Essays24.com - Term Papers and Free Essays
Search

Cmgt 575 - It Project Management for Kudler Fine Foods

Essay by   •  December 17, 2015  •  Research Paper  •  3,166 Words (13 Pages)  •  1,387 Views

Essay Preview: Cmgt 575 - It Project Management for Kudler Fine Foods

Report this essay
Page 1 of 13

        

IT Project Management Report

Tony Rumford, Juliet Okereke, Joshua Crider, Timothy Willbanks

CMGT575

November 23, 2015

Nancy Mingus



IT Project Management

Introduction

For the reorganization of Kudler Fine Foods to be successful, an enterprise system is needed.  The following paper will first discuss the scope of the Enterprise Resource Planning (ERP) system.  Next, it will give the activity and milestone list for the project. Followed by discussing, the work breakdown structure (WBS), for the implementation of the system. Next it will discuss the cost baseline for the project and the schedule baseline as well. Next it will discuss the list of stakeholders, their jobs on the team, and an analysis of their objectives and strategies.

Scope document

        The enterprise system also known as ERP integrates business processes across departments and functions of an organization into one IT system (Business Information Systems, N.D.). This prevents fragmented information but rather stored together in a comprehensive data repository is used by different part of the company (Robbins & Judge, 2011). The ERP system will be crucial for Kathy in effectively planning all aspects of Kudler Fine Foods. She will be able to control the resources of the company from one system. As she currently controls all of the ordering, the ERP system will allow her to know when and where more products need to be ordered and shipped. As certain items in a location get low, they will be easily replaced to meet the demands of the customer. The replacement happens by linking the inventory in each location with the point of sale system, informing Kathy or her manager's inventory levels are low. As KFF company continues to grow this will be useful for online ordering. This will allow a customer to place orders for pick up at the location of his or her choice based on the inventory in that store. Once there is an order, it is sent to the specific location and prepared for the customer by the employee. With the use of the ERP system, the customer will know the order is ready for pickup. This is important as it allows the company to offer more services and options to the customer.

        The ERP system will ensure that Kathy is not only able to maintain inventory levels, but also maintain her employees. The use of one system allows all information compiled and intergraded together. This information will be useful in determining the best time to staff her location based on purchasing habits and trends. Because the ERP system obtains all information into one system Kathy and her managers will be able to determine what time and day's employees should work. This could also help determine if she needs to increase or decrease her staff based on the locations performance. In the reorganization of Kudler Fine Foods, the ERP system allows the company to plan strategically how each location is staffed to ensure the world class experience.

Activity and Milestone list

[pic 1]

Figure 1

BASELINE SCHEDULE

Task Name

Duration

Baseline Start

Baseline Finish

1

Evaluate Current Technology Platform

5 days

Mon 11/9/15

Tue 11/13/15

2

Define User Requirements

2 days

Tue 11/10/15

Mon 11/16/15

3

Design Intranet User Security Levels

4 days

Mon 11/16/15

Thu 11/19/15

4

Designs Web Page Interface Layout

4 days

Wed 11/18/15

Mon 11/23/15

5

Setup Server

3 days

Fri 11/20/15

Tue 11/24/15

6

Estimate Web Traffic

2 days

Mon 11/23/15

Tue 11/24/15

7

Test Web Pages and Links

4 days

Tue 11/24/15

Fri 11/27/15

8

Move Web Page to Production Environment

3 days

Wed 11/25/15

Fri 11/27/15

9

Write Announcement of Intranet for Corporate Newsletter

2 days

Thu 11/26/15

Fri 11/27/15

10

Implement at all Store Locations

7 days

Wed 11/25/15

Fri 12/4/15

11

Test Program ERP System

5 days

Mon 11/30/15

Fri 12/4/15

12

Document After Test is Compiled

2 days

Thu 12/3/15

Fri 12/4/15

14

Train Users

5 days

Fri 12/4/15

Thu 12/10/15

15

Write a Report on Management

1 day

Thu 12/10/15

Thu 12/10/15        

16

Signoff

1 day

Thu 12/10/15

Thu 12/10/15

Figure 2 

List of stakeholders

...

...

Download as:   txt (20.3 Kb)   pdf (428.8 Kb)   docx (46.3 Kb)  
Continue for 12 more pages »
Only available on Essays24.com