Information Technology
Essay by rensacofino • July 17, 2015 • Study Guide • 804 Words (4 Pages) • 1,075 Views
PRODUCING THE PROJECT SCHEDULE
Activity- is made up of a group of related tasks or other smaller activities; also
identified, named, and scheduled
Task- is the smallest piece of work that is identified and scheduled
3 main steps in developing a project schedule
- Develop a work breakdown structure.
- Build a schedule using a Gantt chart.
- Develop resource requirements and the staffing plan.
DEVELOPING A WORK BREAKDOWN STRUCTURE
Work breakdown structure (WBS) - is simply a list of all the required individual activities and tasks for the project; activities that were identified earlier as the key activities for project planning; the hierarchy of phases, activities, and tasks of a project; one method to estimate and schedule the tasks of a project
2 general approached for building a WBS
- By deliverable – identifies immediate and final deliverable that must be developed and necessary task to create the deliverable
- By a sequential timeline – normal sequence of activities that are required to perform the final deliverable
4 most effective techniques for identifying the tasks of the WBS
- Top-down: Identifying major activities first and then listing internal tasks
- Bottom-up: Listing all the tasks you can think of and organizing them later
- Template: Using a standard template of tasks for projects that are fairly standard
- Analogy: Finding a similar, or analogous, project that is finished and copying its tasks
*template or analogy is used if possible but top-down and bottom-up can be used to brainstorm a good list of tasks
4 levels of WBS
- Top level – overall iteration
- 2nd level – major deliverables
- 3rd level – major activities
- 4th level – individual tasks
DEVELOPING THE SCHEDULE
- Both steps are estimated at lowest level on each vertical branch
1st step – identify dependencies between the tasks
*dependencies – identify which tasks must be complete first or must precede other tasks (predecessor & successor tasks)
Common ways to relate tasks
Finish-start relationship
Start-start relationship
Finish-finish relationship
*these three are adjusted to include lead/lag time
2nd step – estimate the actual employee effort required for each task
PERT/CPM Chart - a technique for scheduling a project based on individual tasks or activities
GANTT Chart - a technique for scheduling a project based on individual tasks or activities
Critical Path - a sequence of tasks that cannot be delayed without causing the project to be completed late
Slack Time / Float - the amount of time a task can be delayed without affecting the project schedule
Milestone - a precise point on the project schedule that indicates a specific completion point; is often accompanied by a deliverable or end-product
DEVELOPING THE RESOURCE REQUIREMENT AND STAFFING THE PLAN
SCHEDULING THE ENTIRE SDLC
IDENTIFYING PROJECT RISKS AND CONFIRMING PROJECT FEASIBILITY
Project feasibility analysis - is an activity that verifies whether a project can be started and successfully completed; reasonable chance of success; identifies all risks of failure
...
...